| Jul 11, 2024 | Devices · Radiation Control and Health Safety ActDevices · Postmarket Assurance: Devices; Devices · Compliance: Devices | 4 cited references- 21 CFR 820.30(g). Design Validation - Risk analysis not performed/inadequate Risk analysis is inadequate.
- 21 CFR 820.198(a). Lack of or inadequate complaint procedures Procedures for receiving, reviewing, and evaluating complaints by a formally designated unit have not been adequately established.
- 21 CFR 820.50. Purchasing controls, Lack of or inadequate procedures Procedures to ensure that all purchased or otherwise received product and services conform to specified requirements have not been adequately established.
- 21 CFR 820.30(g). Design validation - software validation not performed Validation of device software is inadequate.
| Official Action Indicated (OAI) |
| Dec 20, 2017 | Devices · Radiation Control and Health Safety ActDevices · Postmarket Assurance: Devices; Devices · Compliance: Devices | 2 cited references- 21 CFR 806.20(b)(4). Justification for not reporting A justification for not reporting the correction or removal action to FDA that included conclusions, follow-ups and reviews by a designated person was not included in the record.
- 21 CFR 820.100(a). Lack of or inadequate procedures Procedures for corrective and preventive action have not been established.
| No Action Indicated (NAI) |
| Oct 6, 2014 | Devices · Compliance: Devices | 9 cited references- 21 CFR 1002.20(a). Failure to report You did not immediately report to the Director, CDRH, FDA, an accidental radiation occurrence reported to or otherwise known to you. involving a product introduced or intended to be introduced into commerce by you.
- 21 CFR 820.198(a). Lack of or inadequate complaint procedures Procedures for receiving, reviewing, and evaluating complaints by a formally designated unit have not been established.
- 21 CFR 820.75(a). Lack of or inadequate process validation A process whose results cannot be fully verified by subsequent inspection and test has not been adequately validated according to established procedures.
- 21 CFR 820.25(b). Training - Lack of or inadequate procedures Procedures for training and identifying training needs have not been adequately established.
- 21 CFR 820.22. Quality audits - Lack of or inadequate procedures Procedures for quality audits have not been adequately established.
- 21 CFR 1003.10(a). FDA not notified of defect or noncompliance You did not notify the Secretary, in accordance with 21 CFR 1003.20, of an electronic product which was defective which you produced, assembled, and distributed.
- 21 CFR 1020.30(g). Providing adequate assembly information Instructions for assembly, installation, adjustment, and testing of components adequate to assure that the product will comply with the regulations, when assembled and tested as directed, was not provided to assemblers
- 21 CFR 820.50. Purchasing controls, Lack of or inadequate procedures Procedures to ensure that all purchased or otherwise received product and services conform to specified requirements have not been adequately established.
- 21 CFR 820.100(a). Lack of or inadequate procedures Procedures for corrective and preventive action have not been established.
| Voluntary Action Indicated (VAI) |
| May 14, 2012 | Devices · Compliance: Devices | 19 cited references- 21 CFR 820.50. Purchasing controls, Lack of or inadequate procedures Procedures to ensure that all purchased or otherwise received product and services conform to specified requirements have not been established.
- 21 CFR 820.40. Lack of procedures, or not maintained Document control procedures have not been established.
- 21 CFR 820.75(a). Lack of or inadequate process validation A process whose results cannot be fully verified by subsequent inspection and test has not been adequately validated according to established procedures.
- 21 CFR 820.75(b). Lack/Inad procedure-Monitoring/Control of Validated Proces Procedures for monitoring and control of process parameters for a validated process have not been adequately established.
- 21 CFR 820.100(a). Lack of or inadequate procedures Procedures for corrective and preventive action have not been established.
- 21 CFR 820.198(c). Investigation of device failures Complaints involving the possible failure of a device to meet any of its specifications were not evaluated and investigated where necessary.
- 21 CFR 820.200(a). Servicing - Lack of or inadequate procedures Procedures or instructions for performing servicing activities and verifying that servicing meets specified requirements have not been adequately established.
- 21 CFR 820.170(a). Lack of or inadequate instructions Installation instructions have not been adequately established.
- 21 CFR 820.80(e). Documentation Acceptance activities were not adequately documented.
- 21 CFR 1002.20(a). Failure to report You did not immediately report to the Director, CDRH, FDA, an accidental radiation occurrence reported to or otherwise known to you. involving a product introduced or intended to be introduced into commerce by you.
- 21 CFR 820.20(a). Management ensuring quality policy is understood Management with executive responsibility has not ensured that the quality policy is understood, implemented and maintained at all levels of the organization.
- 21 CFR 1003.10(a). FDA not notified of defect or noncompliance You did not notify the Secretary, in accordance with 21 CFR 1003.20, of an electronic product which was defective which you produced, assembled, and distributed.
- 21 CFR 1010.2(c). Certification not based on adequate test/testing program Certification was not based upon a testing program in accordance with good manufacturing practices.
- 21 CFR 1003.10(b). Dealers, distributors, purchasers not notified You did not notify the purchasers and subsequent transferees of an electronic product which was defective .
- 21 CFR 820.80(b). Lack of or inadequate receiving acceptance procedures Procedures for acceptance of incoming product have not been established.
- 21 CFR 820.25(b). Training records Personnel training is not documented.
- 21 CFR 820.90(b)(2). Product rework procedures, Lack of or inadequate procedures Procedures for rework of nonconforming product have not been established.
- 21 CFR 1004.1. CAP not submitted In a situation where an electronic product you have manufactured has a defect subject to the notification requirements of 21 CFR 1003.10(b), you have not submitted a plan to the Secretary to without charge (including reimbursement of any transportation expenses), replace the product with a like or equivalent one which, or refund the cost of the product to the purchaser.
- 21 CFR 820.70(a). Production processes Production processes were not conducted to ensure that a device conforms to its specifications.
| Official Action Indicated (OAI) |
| Apr 29, 2011 | Devices · Compliance: Devices | 31 cited references- 21 CFR 1020.30(h)(3)(v). Generator rating and duty cycle A statement of the generator rating and duty cycle was not provided to purchasers.
- 21 CFR 820.75(a). Lack of or inadequate process validation A process whose results cannot be fully verified by subsequent inspection and test has not been adequately validated according to established procedures.
- 21 CFR 1020.30(d)(1). Report of assembly submitted within 15 days A completed report of assembly regarding certified components installed in a diagnostic x-ray system was not submitted to the Director, CDRH, the purchaser, and the State agency responsible for radiation protection within 15 days following the completion of the assembly.
- 21 CFR 1020.30(h)(4)(i). leakage technique factors, beam limiting device A statement of the leakage technique factors for all combinations of tube housing assemblies and beam-limiting devices, for which you state compatibility, was not provided to the users or to others upon request at cost,
- 21 CFR 1020.30(h)(3)(i). Rated line voltage, range (x-ray control + generator) A statement of the rated line voltage and the range of line-voltage regulation for operation at maximum line current was not provided to purchasers.
- 21 CFR 1020.30(h)(2)(i). Tube housing assembly mandatory information Statements for each tube housing assembly of the minimum filtration permanently in the useful beam expressed as millimeters of aluminum equivalent and the peak tube potential at which the aluminum equivalent was obtained were not provided to purchasers
- 21 CFR 1002.10. Failure to submit, distinct marking You did not submit a required product report prior to the introduction of the product into commerce.
- 21 CFR 820.100(a). Lack of or inadequate procedures Procedures for corrective and preventive action have not been established.
- 21 CFR 1020.30(h)(3)(vi). Fixed technique factors--max deviation from nominal In the case of fixed technique factors, a statement of the maximum deviation from the nominal fixed value of each factor was not provided to purchasers.
- 21 CFR 820.198(b). Rationale documented for no investigation Records for complaints where no investigation was made do not include required information.
- 21 CFR 1020.33(f)(1). CT conditions of operation indicated prior to scan The CT conditions of operation to be used during a scan or scan sequence are not indicated prior to initiation of the scan or scan sequence.
- 21 CFR 820.20(a). Management ensuring quality policy is understood Management with executive responsibility has not ensured that the quality policy is understood, implemented and maintained at all levels of the organization.
- 21 CFR 1020.30(h)(4)(i). Beam limiting devices--leakage technique factors Leakage technique factors for all combinations of tube housing assemblies and beam-limiting devices for which the beam-limiting device manufacturer states compatibility are not provided for each variable-aperture beam-limiting device to purchasers.
- 21 CFR 1002.13. Failure to submit You did not submit an annual report for products requiring one.
- 21 CFR 1020.33(c)(3). Performance data for CT conditions of operation - incomplete Performance data for the CT conditions of operation used to provide the information required by 21 CFR 1020.33(c)(2)(i) are incomplete.
- 21 CFR 820.80(b). Lack of or inadequate receiving acceptance procedures Procedures for acceptance of incoming product have not been established.
- 21 CFR 820.198(c). Investigation of device failures Complaints involving the possible failure of a device to meet any of its specifications were not evaluated and investigated where necessary.
- 21 CFR 1020.33(c)(2)(ii). CTDI for conditions of operation which vary exposure The computed tomography dose index (CTDI) in the center location of the dosimetry phantom is not provided to users for each selectable condition of operation that varies either the rate or duration of x-ray exposure.
- 21 CFR 1010.2(c). Certification not based on adequate test/testing program Certification was not based upon a testing program in accordance with good manufacturing practices.
- 21 CFR 1020.30(k). Compliance measurements--diagnostic source assembly Compliance for radiation leakage from the diagnostic source assembly was not determined by measurements averaged over an area of 100 square centimeters with no linear dimension greater than 20 centimeters.
- 21 CFR 1003.10(a). FDA not notified of defect or noncompliance You did not notify the Secretary, in accordance with 21 CFR 1003.20, of an electronic product which was defective which you produced, assembled, and distributed.
- 21 CFR 820.72(a). Calibration, Inspection, etc. Procedures Lack of or Inadequ Procedures to ensure equipment is routinely calibrated, inspected, checked, and maintained have not been established.
- 21 CFR 1020.30(h)(3)(ii). Maximum line current (x-ray control + generator) A statement of the maximum line current of the x-ray system based on the maximum input voltage and output current characteristics of the tube housing assembly compatible with rated output voltage and rated current characteristics of the x-ray control and associated high-voltage generator was not provided to purchasers.
- 21 CFR 820.50. Purchasing controls, Lack of or inadequate procedures Procedures to ensure that all purchased or otherwise received product and services conform to specified requirements have not been established.
- 21 CFR 1020.33(c)(2)(i)(c). CTDI at 90, 180, 270 degrees The computed tomography dose index (CTDI) is not provided to users for locations along lines parallel to the axis of rotation and 1.0 cm interior to the surface of the phantom, at positions 90, 180, and 270 degrees from the position specified in 21 CFR 1020.33(c)(2)(i)(b).
- 21 CFR 1020.30(c). Combination of two or more components Prior written authorization to certify a combination of two or more components when installed into a diagnostic x-ray system was not obtained from CDRH.
- 21 CFR 1003.10(b). Dealers, distributors, purchasers not notified You did not notify all of the purchasers and subsequent transferees of an electronic product which was defective .
- 21 CFR 1002.20(a). Failure to report You did not immediately report to the Director, CDRH, FDA, an accidental radiation occurrence reported to or otherwise known to you. involving a product introduced or intended to be introduced into commerce by you.
- 21 CFR 1004.1. CAP not submitted In a situation where an electronic product you have manufactured has a defect subject to the notification requirements of 21 CFR 1003.10(b), you have not submitted a plan to the Secretary to remedy the defect without charge (including reimbursement of any transportation expenses), replace the product with a like or equivalent one which is free of defects relating to safety of its use, or refund the cost of the product to the purchaser.
- 21 CFR 1020.30(h)(3)(viii). Measurement criteria for technique factors A statement describing the measurement criteria for all technique factors used was not provided to purchasers.
- 21 CFR 820.30(i). Design changes - Lack of or Inadequate Procedures Procedures for design change have not been established.
| Official Action Indicated (OAI) |
| Oct 14, 2010 | Devices · Postmarket Assurance: DevicesDevices · Compliance: Devices | 8 cited references- 21 CFR 803.17. Lack of Written MDR Procedures Written MDR procedures have not been implemented.
- 21 CFR 820.22. Quality audits - Lack of or inadequate procedures Procedures for quality audits have not been adequately established.
- 21 CFR 820.50(a). Evaluation of suppliers, contractors, etc., requirements Requirements that must be met by suppliers have not been established.
- 21 CFR 820.20(a). Management ensuring quality policy is understood Management with executive responsibility has not ensured that the quality policy is understood, implemented and maintained at all levels of the organization.
- 21 CFR 806.10(a)(1). Report of risk to health A correction or removal, conducted to reduce a risk to health posed by a device, was not reported in writing to FDA.
- 21 CFR 820.198(b). Review and evaluation for investigation Not all complaints have been reviewed and evaluated to determine whether an investigation is necessary.
- 21 CFR 820.100(a). Lack of or inadequate procedures Procedures for corrective and preventive action have not been adequately established.
- 21 CFR 1003.10(a). FDA not notified of defect or noncompliance You did not notify the Secretary, in accordance with 21 CFR 1003.20, of an electronic product which was defective which you produced, assembled, and distributed.
| Official Action Indicated (OAI) |
| Mar 4, 2009 | Devices · Postmarket Assurance: DevicesDevices · Compliance: Devices | 19 cited references- 21 CFR 820.30(g). Design validation - software validation not performed Validation of device software is incomplete.
- 21 CFR 820.30(e). Design review - documentation The design review results, including identification of the design, the date, and the individual performing the review, were not documented and filed in the design history file.
- 21 CFR 820.30(g). Design validation- Lack of or inadequate procedures Procedures for validating the device design were not complete.
- 21 CFR 820.30(c). Design input approval documentation The approval of design input requirements (including the date and signature of the individual approving the requirements) was not documented.
- 21 CFR 820.30(h). Design transfer - Lack of or inadequate procedures Procedures were not documented to ensure that the device design was correctly transferred into production.
- 21 CFR 820.30(i). Design changes - validation vs. verification Procedures were not documented to address when verification of design changes is sufficient in lieu of validation prior to their implementation.
- 21 CFR 820.181(a). DMR device specifications The device master record does not include or refer to the location of all, device, and software specifications.
- 21 CFR 820.20(a). Management ensuring quality policy is understood Management with executive responsibility has not ensured that the quality policy has been fully implemented and maintained at all levels of the organization.
- 21 CFR 820.181. DMR - not or inadequately maintained The device master record does not include or refer to the location of installation procedures and methods.
- 21 CFR 820.30(d). Design output - review and approval The approval of design output (including the date and signature of the individual approving the output) was not documented.
- 21 CFR 820.120(b). DHR documentation of label release {see also 820.184} The DHR does not include records of approval and release of device labeling, including date and signature of the examiner.
- 21 CFR 820.90(a). Nonconforming product evaluation/investigation The investigation of nonconforming product has not been documented.
- 21 CFR 820.40(a). Not approved or obsolete document retrieval Documents that were not approved were observed at a location where they are being used.
- 21 CFR 820.184. DHR content The device history record does not demonstrate the device is manufactured in accordance with the device master record.
- 21 CFR 820.30(b). Establish the design and development plan A design and development plan has not been documented.
- 21 CFR 820.184(e). ID label, labeling The device history record does not include the primary identification label and labeling for each device.
- 21 CFR 820.70(a)(4). Approval of process Processes have not been approved.
- 21 CFR 820.50(b). Approval of purchasing data {see also 820.40(a)} The purchasing data were not approved.
- 21 CFR 820.30(f). Design verification procedures Procedures for verifying that design output meets design input were not complete.
| Voluntary Action Indicated (VAI) |